Project: Attenuation tank installation, Tesco Distribution Centre, Magor, South Wales
Product Profile:GEOlightTM 400. 969m3
Location:Tesco Distribution Centre, Magor, South Wales
Type of job:Full installation
Date Completed: Tuesday 31st January
Summary: The installation consisted on two attenuation tanks of 600m3 and 300m3. A distributor pipe ran off centre through the modular system. Dimensions of tank 1 was length ~ 105metres, Width 11.5 metres, height 0.5 metres= 600m3. Tank 2 length 53 metres, Width 11.5 metres, height 0.5 metres = 300m3. Also fitted as part of the installation was pipework, membranes, geotextiles, air ventilation system, top-hat system and aggregate filling.
Contractor:Smiths Gloucester Construction Limited contracted to Brittannia .
Download PDF
View comparison
Technical Data Sheet
Technical enquiries

Smith’s Gloucester, contracted to Brittania needed a 969m3 storm water management system for a new Tesco distribution centre in Magor, South Wales. Two of the key issues were speed of installation, and loading capacity as the system needed to be located underneath the HGV service yard.

It was decided by the design engineer and the contractor that the GEOlightTM storm water management package offered by Sustainable Drainage Systems Ltd provided the most cost effective solution in terms of performance, buildability and cost. GEOlightTM, our low-weight, modular, honeycombed structure, made from 100% recycled PVC, offers 95% water retention void, fewer distribution pipes and manholes, and also reduced excavation over other systems.

During installation it emerged that a 55 tonne piling rig had to be trafficked over the GEOlightTM system. This was achieved with no disruption to the installation or programme of works on site.

 
The Geomembrane and the Geotextile is laid within the excavated area.
The GEOlightTM modular blocks are rapidly and easily installed.
As part of the ongoing installation procedure, the Geotextile and Geomembrane is laid on top of the tank as it is being installed.
Pipe work is quickly installed, and backfilling begins. Diggers are able to backfill while sitting directly on the tank due to GEOlightTM's unique design and strength.
The pipe work is backfilled and wrapped in a membrane for this project, while installation and backfilling of the tank continues.
The tank is installed and backfilled within days, allowing the contractor to continue the construction of the distribution centre. Note: The tank's length spanned down the visible fence as it was a 969m3 project.
Latest News
U.K`s largest modular attenuation tank - In Pictures
27 November 2008
SDS Complete Cardiff Re-development
14 April 2008
GEOlight reduces construction carbon footprint
21 December 2007
GEOsystems installs largest modular attenuation tank in Ireland
21 December 2007
GEOlight shows its strength
23 November 2007